#DateTypeDetailsFurnaceEquipmentActions
669114 Oct 2023Scheduled MaintenanceWASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.
5. check the high mast lights also.
OtherWASHING PLANT
669213 Oct 2023Scheduled MaintenanceF1- ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.

Furnace IELECTRODE 1
669313 Oct 2023Scheduled MaintenanceF1- ELECTRODE BLOWER 2

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
Furnace IELECTRODE 2
669413 Oct 2023Scheduled MaintenanceF1- ELECTRODE BLOWER 3

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.

Furnace IELECTRODE 3
669513 Oct 2023Scheduled MaintenanceFURNACE 1

1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.

Furnace IHYDRAULIC POWER PACK NO. 1
669613 Oct 2023Scheduled MaintenanceFURNACE 1

1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.
Furnace IHYDRAULIC POWER PACK NO. 2
669713 Oct 2023Scheduled Maintenance ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
Furnace IIELECTRODE 1
669813 Oct 2023Scheduled MaintenanceELECTRODE BLOWER 2

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
Furnace IIELECTRODE 2
669913 Oct 2023Scheduled Maintenance ELECTRODE BLOWER 3

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
Furnace IIELECTRODE 3
670013 Oct 2023Scheduled MaintenanceFURNACE 2
1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.
Furnace IIHYDRAULIC POWER PACK NO. 1