| 16661 | 17 Mar 2020 | Scheduled Maintenance | Granulation tank no 1
Pump no 1
Gland rope fitting is done. | Other | OTHERS | |
| 16662 | 17 Mar 2020 | Breakdown Maintenance | Washing plant crusher
Its spring rod is broken.
So it's in breakdown. | Other | OTHERS | |
| 16663 | 17 Mar 2020 | Breakdown Maintenance | Lab muffle furnace new coil received.
It's fitted inside the muffle furnace and testing is ok up to 900 degree temp. | Other | OTHERS | |
| 16664 | 17 Mar 2020 | Breakdown Maintenance | Washing plant convenor no 1
Limit switch is broken.
So we check the connection and fit it properly. | Other | OTHERS | |
| 16665 | 17 Mar 2020 | Scheduled Maintenance | Washing plant panel cleaning ,checking and all loose connection tighting. | Other | OTHERS | |
| 16666 | 16 Mar 2020 | Breakdown Maintenance | Pollution 1 furnace 1
Water pumps motor fitting is done. Fitting gland rope for prevent from water leakage. | Other | OTHERS | |
| 16667 | 16 Mar 2020 | Scheduled Maintenance | RMHS BELT CONVEYOR
BC 1, BC 4,BC 5, BC 6, BC 7 maintenance is done.
Conveyor no 1 belts condition is not because of material not falling properly from hopper. | Other | OTHERS | |
| 16668 | 16 Mar 2020 | Breakdown Maintenance | pollution no 1 f1
Water pumps motor changed by spare one and checking the connection now it's ok. | Other | OTHERS | |
| 16669 | 16 Mar 2020 | Scheduled Shutdown | heat exchanger fitting is done. | Furnace I | OTHERS | |
| 16670 | 16 Mar 2020 | Scheduled Shutdown | E2
hydraulic oil leakage from the upper clamp slipping cylinder.
we tight the nuts and also solve the slipping problem. | Furnace II | OTHERS | |