Maintenance Report

Search Filter:

Showing 16,651-16,660 of 17,159 items.

#DateTypeDetailsFurnaceEquipmentActions
1665119 Mar 2020Breakdown MaintenanceShipping yard old crane
It's rope pulley broken.
So we change it by 5 ton rope pulley.
OtherOTHERS
1665219 Mar 2020Breakdown MaintenanceWashing plant
Discharge conveyor
Drum changed and gear box servicing is done.
OtherOTHERS
1665318 Mar 2020Breakdown MaintenanceLab muffle furnace
Successfully testing is done.temp. up to 900 degree Celsius
OtherOTHERS
1665418 Mar 2020Scheduled MaintenanceBoth furnaces pollution id fans cleaning and start.OtherOTHERS
1665518 Mar 2020Scheduled MaintenanceFurnace 1
Granulation pump no 2
Motor terminal connection checking and tighting all terminal bolts.
Starter connection also checking and tighting loosen parts.
OtherOTHERS
1665618 Mar 2020Scheduled MaintenanceFurnace 1
Graduation tank no 1
Pump no 1
We open the pump for maintenance and found inside slag and small piece of world.
Impeller condition is not good. Its fins and key section is crecked.we fitting a new key inside the impeller.
OtherOTHERS
1665717 Mar 2020Breakdown MaintenanceWashing plant discharge conveyor flange coupling fitting is done.OtherOTHERS
1665817 Mar 2020Scheduled MaintenanceWashing plant crusher
Greasing is done. Also loosen belt is tight.
OtherOTHERS
1665917 Mar 2020Breakdown MaintenanceHeat exchanger water pipe line fitting is done.Furnace IOTHERS
1666017 Mar 2020Scheduled Maintenance Granulation tank 1
Pump no 2
Impeller fitting is done. Testing is ok.
OtherOTHERS