| 16571 | 04 Apr 2020 | Scheduled Shutdown | Electrode blower and seal cooling blower
Its motor and starter cheking and loose parts tighting is done. | Furnace I | OTHERS | |
| 16572 | 03 Apr 2020 | Scheduled Shutdown | 3 vertical slipping cylinder seal changing is done. | Furnace I | OTHERS | |
| 16573 | 03 Apr 2020 | Scheduled Shutdown | Conveyor gear box open.
Its bearing is not in the store. We changed its motor bearing. | Other | OTHERS | |
| 16574 | 03 Apr 2020 | Scheduled Shutdown | Charing chutes welding work is done. | Furnace I | OTHERS | |
| 16575 | 03 Apr 2020 | Scheduled Shutdown | Bus bar work is in progress. | Other | OTHERS | |
| 16576 | 03 Apr 2020 | Breakdown Maintenance | Shipping yard
New cranes
CT pinion gear is fitting and crane side GEAR BOX fitting is done.now it's working. | Other | OTHERS | |
| 16577 | 03 Apr 2020 | Scheduled Shutdown | Transformer oil filtration is in progress. | Furnace I | OTHERS | |
| 16578 | 03 Apr 2020 | Other | Guest house side 2 cfl fitting is done. | Other | OTHERS | |
| 16579 | 03 Apr 2020 | Breakdown Maintenance | Automotive maintenance
Mahindra tractor and tata tipper
Tyre puncher maintenance is done. | Other | OTHERS | |
| 16580 | 02 Apr 2020 | Scheduled Shutdown | RMHS
Conveyor BC 5 AND BC 7
gear box open. | Other | OTHERS | |