| 16521 | 14 Apr 2020 | Breakdown Maintenance | tapping section
crane no 3
its main cable damaged so we replace it by a new 12 meter cable. | Other | OTHERS | |
| 16522 | 14 Apr 2020 | Breakdown Maintenance | submersible pump near the cooling tower starter problem it was repaired. | Other | OTHERS | |
| 16523 | 13 Apr 2020 | Scheduled Maintenance | tapping section crane no 1 and 2
motor and starter maintenance is done. | Other | OTHERS | |
| 16524 | 13 Apr 2020 | Scheduled Maintenance | furnace 2 granulation motor and starter maintenance is done. | Other | OTHERS | |
| 16525 | 13 Apr 2020 | Scheduled Maintenance | washing plant panel board clean and lose connection tightening. | Other | OTHERS | |
| 16526 | 13 Apr 2020 | Scheduled Maintenance | Washing plant crusher
We greasing it. | Other | OTHERS | |
| 16527 | 11 Apr 2020 | Scheduled Shutdown | Control desh panel board blowering check and tighten all connection.
| Other | OTHERS | |
| 16528 | 11 Apr 2020 | Scheduled Shutdown | Cooling tower motor 1,2 maintenance done and starter connection also check & tighten.
| Other | OTHERS | |
| 16529 | 11 Apr 2020 | Scheduled Shutdown | Vaibro feeder panel board and PLC panel blowering and tighten all connection. | Other | OTHERS | |
| 16530 | 11 Apr 2020 | Scheduled Shutdown | Cooling tower pipe fitting is done. Nozzle fitting is reasoning.
| Other | OTHERS | |