Maintenance Report

Search Filter:

Showing 16,501-16,510 of 17,159 items.

#DateTypeDetailsFurnaceEquipmentActions
1650116 Apr 2020Breakdown Maintenancefurnace 2 pollution water tank
motor coil is burning it was removed and we do rewinding.
OtherOTHERS
1650216 Apr 2020Scheduled Maintenancecontact clamp welding is done.OtherOTHERS
1650316 Apr 2020Breakdown Maintenancefurnace 2
The pollution pump is ready.
OtherOTHERS
1650416 Apr 2020Scheduled Maintenancefurnace 1
granulation tank
we mount one 20 mm plate to preventing the pipeline and cover the pipeline hole.
OtherOTHERS
1650516 Apr 2020Otherpressure ring making work is in progress.OtherOTHERS
1650615 Apr 2020Breakdown MaintenanceWe change one padestal bearing at talking section trolly side.OtherOTHERS
1650715 Apr 2020Breakdown MaintenanceShopping yard
New screening machine
Its one spring damaged. Now it is in break down.
OtherOTHERS
1650815 Apr 2020Scheduled MaintenanceWe check all solenoid valves of charging chutes for F1 and F2.
Some valves pipe is dameged so we repaired it.
OtherOTHERS
1650915 Apr 2020Scheduled MaintenanceGranulation tank for F1
It's work is done.but some slag is stuck in the pipe so we remove it.now water flow is ok.
OtherOTHERS
1651015 Apr 2020Breakdown MaintenanceAutomotive maintenance
Tata tipper tyre puncher maintenance is done.we fix one gater into the tyre.
OtherOTHERS