#DateTypeDetailsFurnaceEquipmentActions
1648120 Apr 2020Breakdown MaintenanceF2 telpher
Push button not working g it was changed.
OtherOTHERS
1648220 Apr 2020Other2 D.O.L
For mansa washing plant it is ready and checked.
OtherOTHERS
1648318 Apr 2020Breakdown Maintenancefurnace 2
Pollution
We fit one pump and now it's working.
OtherOTHERS
1648418 Apr 2020OtherOne Pressure ring fabircation work is complete.OtherOTHERS
1648518 Apr 2020Scheduled MaintenanceVibro feeder side checking and maintenance done.OtherOTHERS
1648618 Apr 2020Scheduled MaintenanceShipping yard
Both cranes bus bar work is finish.now both cranes working from bus bar.
OtherOTHERS
1648718 Apr 2020Breakdown MaintenanceFurnace 2
Pollution
Motor check and connection given.
OtherOTHERS
1648818 Apr 2020OtherMansa washing plant
2 nos D.O.L. starter wiring complete and checked.
OtherOTHERS
1648918 Apr 2020Breakdown MaintenanceAutomotive maintenance
Tafe tractor
It's clutch plate is damage . So we repaired it and fit.
OtherOTHERS
1649018 Apr 2020Scheduled MaintenanceWASHING PLANT
TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR

1. checked the motor condition ( amp, volt, and connectivity) no noise coming.
2. checked panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. all limit switches and wires working properly.
5. checked the street lights.
OtherOTHERS