| 16191 | 19 May 2020 | Breakdown Maintenance | It's bucket lock pin is damaged. So we change it by nee one bolt. | Other | JCB 4DX | |
| 16192 | 19 May 2020 | Breakdown Maintenance | Pump no 2 motor connector kit damaged. it is repaired. Now it's working. | Other | GRANULATION TANK (FURNACE 2) | |
| 16193 | 19 May 2020 | Breakdown Maintenance | Tapping side granulation motor push button not working. It's change now it's ok. | Furnace II | GRANULATION TANK (FURNACE 2) | |
| 16194 | 18 May 2020 | Other | WATER FILTER WORK IS done. | Other | WATER FILTER | |
| 16195 | 18 May 2020 | Scheduled Maintenance | ALL CONVEYORS
BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. IT IS OK.
2. check panel board, clean, & tight all loose parts. CLEAN AND TIGHTENING ALL LOOSE PARTS.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.IT IS OK.
| Other | RMHS CONVEYOR | |
| 16196 | 18 May 2020 | Scheduled Maintenance | ALL VIBRATORS
check Vibro feeders coil connection, its condition and ensure its working properly with adjusting its vibrations.CHECKING AND ADJUSTING VIBRATION IS DONE. IT IS OK. | Other | RMHS VIBRO FEEDER | |
| 16197 | 18 May 2020 | Scheduled Maintenance | ALL CONVEYORS
BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7
1. greasing of bearings. it is done.
2. lubrication of rollers and check conditions. it is ok.
3. check belt status ( if damaged than inform and change) and also check tightness, speed. ALL BELT CONVEYORS CONDITION IS OK EXCEPT BC 2. WE NEED TO CHANGE IT. WE INFORM IT TO HOD. WE CHANGE IT AS SOON AS POSSIBLE.
4. gearbox oil level check and if not then fill as per requirement. ALL GEARBOX ARE OK.
5. check coupling and key ( if damaged than inform and change) and do the greasing. IT IS OK. GREASING IS DONE.
6. check the drum condition. IT IS OK.
7. check mounting frame welding condition. IT IS OK.
8. check rollers condition and if not good then change.
| Other | RMHS CONVEYOR | |
| 16198 | 18 May 2020 | Other | One spare contact clamp welding is done. | Other | CONTACT CLAMP (SPARE) | |
| 16199 | 18 May 2020 | Other | ONE SPARE CONTACT CLAMP CASTING IS DONE. | Other | CONTACT CLAMP (SPARE) | |
| 16200 | 18 May 2020 | Breakdown Maintenance | Batching discharge vivek feeder not working. So we check it and it's power line repaired. Alignment also done. Now it's ok. | Other | RMHS VIBRO FEEDER | |