| 15771 | 29 Jun 2020 | Breakdown Maintenance | Its contact clamp no. B2 side small leukage. We put pulp. Now its ok. | Furnace I | ELECTRODE 2 | |
| 15772 | 29 Jun 2020 | Breakdown Shutdown | its electrode 1 pressure ring ms pipe is leakage. we weld it. | Furnace I | ELECTRODE 1 | |
| 15773 | 29 Jun 2020 | Breakdown Shutdown | during the shutdown, we clean pollution chimney dust. | Furnace I | POLLUTION 1 | |
| 15774 | 29 Jun 2020 | Breakdown Shutdown | its electrode 1 contact clamp no A4 side water leakage due to pressure ring bolt out. we tight pressure ring bolt. now it's ok. | Furnace II | ELECTRODE 1 | |
| 15775 | 29 Jun 2020 | Breakdown Maintenance | It's universal cross is damaged we mount new one now it's ok. | Other | LODER NO.2 | |
| 15776 | 28 Jun 2020 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE 2 It's H.T. MOTOR IS BURN. ELECTRICAL DEP. WORKING ON IT. LT. 1. check coupling, shaft, and pedestal bearing condition and do the greasing.greaaing is done. 2. check the gearbox oil level, leakage, and fill if required.SMALL AMOUNT OF GRESE FILLING IS DONE. 3. check all fasteners and mounting bolts.IT IS OK. 4. check frame welding conditions.IT IS OK. 5. check end traveling gears condition and do the greasing.IT IS OK. GREASING IS DONE. CT. 1. check coupling, shaft, and pedestal bearing condition and do the greasing.IT IS OK. 2. check the gearbox oil level, leakage, and fill if required.GREASE FILLING IS DONE. 3. check all fasteners and mounting bolts.IT IS OK. 4. check frame welding conditions.IT IS OK. 5. check end traveling gears condition and do the greasing.IT IS OK. GREASEING IS DONE. HT. ITS MOTOR IS BURN. ELET. DEP. WORKING ON IT. 1. check rope drum, hook, rope condition. greasing of rope.IT IS OK. GREASING IS DONE. 2. check the thruster drum condition and its brake tightness. 3. check all fasteners and mounting bolts.IT IS OK. 4. check frame welding conditions. IT IS OK. | Other | TAPPING SEC. CRANE NO. 2 | |
| 15777 | 27 Jun 2020 | Other | jigging machine work is complete. | Other | JIGGING MACHINE | |
| 15778 | 27 Jun 2020 | Scheduled Maintenance | TILTING HOPPER 1. greasing all bushes.greasing is done. 2.hydraulic pump and motor coupling.it is ok. 3. checking the hydraulic oil level and if not then fill.oil level is ok. 4. check hopper welding sections. Welding condition is ok. CONVEYOR NO 1 1. greasing of bearings.greasing is done. 2. lubrication of rollers and check conditions.greasing of all rollers is done.we change 5nos rollers. 3. check belt status ( if damaged than inform and change) and also check tightness, speed.belt is ok.we need to change is after 2 weeks. 4. gearbox oil level check and if not then fill as per requirement.gear box oil level is ok. 5. check coupling and key ( if damaged than inform and change) and do the greasing.greasing of coupling is done. 6. check the drum condition.it is ok. 7. check mounting frame welding condition.it is ok. 8. check rollers condition and if not good then change. CRUSHER crusher is not working due to its plate bolt is broken. 1. check the crusher foundation. 2. check V belts condition. 3. do greasing. 4. check spring rod condition and gap between plates. VIBRATOR 1. check the spring condition.it is ok. 2. check V belts condition.it is ok. 3. check vibrations if not good then adjust.it is ok. 4. check the frame welding condition.it is ok. 5. It's motor power is not enough to run it. We change it to 7.5 hp. Old motor bearing is damaged.we change it. ROLLER 1. check roller speed.its ok. 2.greasing of bearings.greasing is done. 3.gearbox oil level check and if not then fill as per requirement.it is ok. 4. check coupling and key ( if damaged than inform and change) and do the greasing.greasing is done. 5. check the drum condition.it is ok. 6. check the mounting frame welding condition.it is ok. DISCHARGE CONVEYOR 1. greasing of bearings.Greasing is done. 2. lubrication of rollers and check conditions.it is ok.greasong of all rollers is done. 3. check belt status ( if damaged than inform and change) and also check tightness, speed.it is ok. 4. gearbox oil level check and if not then fill as per requirement.small amount of grease filling . 5. check coupling and key ( if damaged than inform and change) and do the greasing.coupling condition is good. Greasing is done. 6. check the drum condition. 7. check mounting frame welding condition.it is ok. 8. check rollers condition and if not good then change. | Other | WASHING PLANT | |
| 15779 | 27 Jun 2020 | Scheduled Maintenance | WASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. Checking of motors it is ok. 2. check panel board, clean, & tight all loose parts. Clean and tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. It's is ok. 5. check the high mast lights also.it is ok. | Other | WASHING PLANT | |
| 15780 | 27 Jun 2020 | Breakdown Shutdown | its electrode no .3 seal box rope is burning so fire coming on the top side. we change the asbestos rope. | Furnace I | ELECTRODE 3 | |