| 15761 | 01 Jul 2020 | Breakdown Maintenance | It's clutch and pressure plate is damaged. We change it with new one.
It's front left wheel cylinder is damaged. We replace it by new one. | Other | ESCORT HYDRA | |
| 15762 | 30 Jun 2020 | Scheduled Maintenance | WATER CIRCULATION PUMP 1,2,3, it is ok. we greasing no. 2 pump.
FURNACE 1
GRANULATION PUMP 1,2 greasing is done on the coupling. we change glad rope of no. 1 pump.
SUBMERSIBLE PUMP 1,2,
POLLUTION WATER PUMP NO 1
its monoblock hole is going big. It leakage too much water.
FURNACE 2
GRANULATION PUMP 1,2, its coupling greasing is done. and we tight gland rope.
POLLUTION WATER PUMP NO 1, its monoblock is leakage too much water.
OFFICE SUBMERSIBLE PUMP 1,
WASHING PLANT SUBMERSIBLE PUMP 1
1. check the pump condition and check discharge.
2. check coupling condition, alignment, and do greasing.
3. check pipelines and valve's condition.
4. check cooling towers nozzles condition. its nozzle condition is good.
| Other | PUMP | |
| 15763 | 30 Jun 2020 | Scheduled Maintenance | F1- GRANULATION MOTOR 1,2 WATER CIRCULATION PUMP MOTOR 1,2,3, SUBMERSIBLE PUMP MOTOR 1,2, POLLUTION WATER PUMP MOTOR
NO 1
F2- GRANULATION MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1, OFFICE SUBMERSIBLE PUMP MOTOR 1,
WASHING PLANT SUBMERSIBLE PUMP MOTOR1
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. check no noise coming.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. water circulation pump motor greasing. greasing is done.
| Other | PUMP | |
| 15764 | 30 Jun 2020 | Breakdown Maintenance | its has heavy vibration. we clean and start. | Other | POLLUTION 2, ID FAN NO. 1 | |
| 15765 | 30 Jun 2020 | Breakdown Maintenance | its conveyor belt is damaged by big size stones. we repair it. now it's ok. | Other | RMHS BELT CONVEYOR NO.6 | |
| 15766 | 30 Jun 2020 | Breakdown Maintenance | slipping cylinder tank oil level is low. we fill 100 ltr hydraulic oil and for hoisting cylinder tank 50 ltr hydraulic oil. | Furnace I | HYDRAULIC POWER PACK NO. 1 | |
| 15767 | 30 Jun 2020 | Breakdown Maintenance | It's front right side spring plate broken. We repaired by welding with one bush and centre bolt new one fitting is done. | Other | TATA TIPPER | |
| 15768 | 29 Jun 2020 | Scheduled Maintenance | ALL CONVEYORS
BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.cheking,clean and tighting all bolts.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.
It's is ok.
BC 6 limit switch wire rope foundation is damaged. Mechanical persons repaired it.now it's ok
| Other | RMHS CONVEYOR | |
| 15769 | 29 Jun 2020 | Scheduled Maintenance | ALL VIBRATORS
check Vibro feeders coil connection, its condition and ensure its working properly with adjusting its vibrations.checking and testing is done. It's ok. | Other | RMHS VIBRO FEEDER | |
| 15770 | 29 Jun 2020 | Scheduled Maintenance | ALL CONVEYORS
BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7
1. greasing of bearings.greasing is done.
2. lubrication of rollers and check conditions.it is ok.
3. check belt status ( if damaged than inform and change) and also check tightness, speed.BC 6 belt repairing. And BC 2 side separator plate fixing.
BC 1 BELT CONDITION IS NOT GOOD. WE CHNAGE IT AFTER 2 WEEKS.
4. gearbox oil level check and if not then fill as per requirement.it is ok
5. check coupling and key ( if damaged than inform and change) and do the greasing.greasing is done.
6. check the drum condition.
7. check mounting frame welding condition.it is ok.
8. check rollers condition and if not good then change.
| Other | RMHS CONVEYOR | |