| 15591 | 17 Jul 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace I | ELECTRODE 1 | |
| 15592 | 17 Jul 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace I | ELECTRODE 2 | |
| 15593 | 17 Jul 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 3
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
| Furnace I | ELECTRODE 3 | |
| 15594 | 17 Jul 2020 | Scheduled Maintenance | FURNACE 1
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves. its ok.
| Furnace I | HYDRAULIC POWER PACK NO. 1 | |
| 15595 | 17 Jul 2020 | Scheduled Maintenance | FURNACE 1
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves. it's ok.
| Furnace I | HYDRAULIC POWER PACK NO. 2 | |
| 15596 | 17 Jul 2020 | Scheduled Maintenance | ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace II | ELECTRODE 1 | |
| 15597 | 17 Jul 2020 | Scheduled Maintenance | ELECTRODE BLOWER 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace II | ELECTRODE 2 | |
| 15598 | 17 Jul 2020 | Scheduled Maintenance | ELECTRODE BLOWER 3
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace II | ELECTRODE 3 | |
| 15599 | 17 Jul 2020 | Scheduled Maintenance | FURNACE 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.it is ok. | Furnace II | HYDRAULIC POWER PACK NO. 1 | |
| 15600 | 17 Jul 2020 | Scheduled Maintenance | FURNACE 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.it is ok. | Furnace II | HYDRAULIC POWER PACK NO. 2 | |