| 15481 | 31 Jul 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace I | ELECTRODE 1 | |
| 15482 | 31 Jul 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace I | ELECTRODE 2 | |
| 15483 | 31 Jul 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 3
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower. | Furnace I | ELECTRODE 3 | |
| 15484 | 31 Jul 2020 | Scheduled Maintenance | FURNACE 1
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves. its ok. | Furnace I | HYDRAULIC POWER PACK NO. 1 | |
| 15485 | 31 Jul 2020 | Scheduled Maintenance | FURNACE 1
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves. its ok. | Furnace I | HYDRAULIC POWER PACK NO. 2 | |
| 15486 | 31 Jul 2020 | Scheduled Maintenance | ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower | Furnace II | ELECTRODE 1 | |
| 15487 | 31 Jul 2020 | Scheduled Maintenance | ELECTRODE BLOWER 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower | Furnace II | ELECTRODE 2 | |
| 15488 | 31 Jul 2020 | Scheduled Maintenance | ELECTRODE BLOWER 3
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower | Furnace II | ELECTRODE 3 | |
| 15489 | 31 Jul 2020 | Scheduled Maintenance | FURNACE 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower
4. check solenoid valves.it is ok. | Furnace II | HYDRAULIC POWER PACK NO. 1 | |
| 15490 | 31 Jul 2020 | Scheduled Maintenance | FURNACE 2
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts.clean and tight all loose parts.
3. all parts clean by hand blower
4. check solenoid valves.it is ok. | Furnace II | HYDRAULIC POWER PACK NO. 2 | |