| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 15421 | 10 Aug 2020 | Other | for Mansa washing plant roller and conveyor making is done. We make one roller ,one conveyor and feeding hopper. It's fitting also done. | Other | BLUE OCEAN | |
| 15422 | 08 Aug 2020 | Scheduled Maintenance | because of no washed material we not doing its maintenance. we doing all maintenance on Tuesday. TILTING HOPPER 1. greasing all bushes. 2.hydraulic pump and motor coupling. 3. checking the hydraulic oil level and if not then fill. 4. check hopper welding sections. CONVEYOR NO 1 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. CRUSHER 1. check the crusher foundation. 2. check V belts condition. 3. do greasing. 4. check spring rod condition and gap between plates. VIBRATOR 1. check the spring condition. 2. check V belts condition. 3. check vibrations if not good then adjust. 4. check the frame welding condition. ROLLER 1. check roller speed. 2.greasing of bearings. 3.gearbox oil level check and if not then fill as per requirement. 4. check coupling and key ( if damaged than inform and change) and do the greasing. 5. check the drum condition. 6. check the mounting frame welding condition. DISCHARGE CONVEYOR 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. | Other | WASHING PLANT | |
| 15423 | 08 Aug 2020 | Scheduled Maintenance | because of no washed material we not doing its maintenance. we doing all maintenance on Tuesday. WASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. 5. check the high mast lights also. | Other | WASHING PLANT | |
| 15424 | 07 Aug 2020 | Breakdown Maintenance | Tyre puncher left back side. It's puncher maintenance is done. | Other | LODER NO.2 | |
| 15425 | 07 Aug 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 1 SEAL COOLING BLOWER 1, 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 1 | |
| 15426 | 07 Aug 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 2 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 2 | |
| 15427 | 07 Aug 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 3 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 3 | |
| 15428 | 07 Aug 2020 | Scheduled Maintenance | FURNACE 1 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. 4. check solenoid valves.its ok. | Furnace I | HYDRAULIC POWER PACK NO. 1 | |
| 15429 | 07 Aug 2020 | Scheduled Maintenance | FURNACE 1 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. 4. check solenoid valves.its ok. | Furnace I | HYDRAULIC POWER PACK NO. 2 | |
| 15430 | 07 Aug 2020 | Scheduled Maintenance | ELECTRODE BLOWER 1 SEAL COOLING BLOWER 1, 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. | Furnace II | ELECTRODE 1 | |