| 15291 | 26 Aug 2020 | Scheduled Maintenance | 3RD FLOOR CARBON PASTE LIFTING CRANE
LT., CT. , HT.
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok.
2. check panel board, clean, & tight all loose parts. Clean and tighten all loose parts.
3. all parts clean by hand blower.
4. No limit switches. | Other | CARBON PASTE LIFTING CRANE | |
| 15292 | 25 Aug 2020 | Scheduled Maintenance | WATER CIRCULATION PUMP 1,2,3,
pump no. 2 is ready.
FURNACE 1
GRANULATION
SUBMERSIBLE PUMP 1,2, PUMP 1,2
it's ok.
POLLUTION WATER PUMP NO 1
It has heavy leakage. we fix it with gland rope. but still leakage. we need new monoblock.
FURNACE 2
GRANULATION PUMP 1,2,
The greasing of coupling is done.
POLLUTION WATER PUMP NO 1, NO.2
it has leakage. we fix the leakage. now it's ok.
NO.2 pump welding side M-seal fitting is done. we fix gland ropes leakage. we fix air leakage also.
OFFICE SUBMERSIBLE PUMP 1,
WASHING PLANT SUBMERSIBLE PUMP 1
washing plant side pump is ok.
1. check the pump condition and check discharge.
2. check coupling condition, alignment, and do greasing.
3. check pipelines and valve's condition.
4. check cooling towers nozzles condition. its condition is ok. | Other | PUMP | |
| 15293 | 25 Aug 2020 | Scheduled Maintenance | F1- GRANULATION MOTOR 1,2 WATER CIRCULATION PUMP MOTOR 1,2,3, SUBMERSIBLE PUMP MOTOR 1,2, POLLUTION WATER PUMP MOTOR
NO 1
F2- GRANULATION MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1, OFFICE SUBMERSIBLE PUMP MOTOR 1,
WASHING PLANT SUBMERSIBLE PUMP MOTOR1
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.check and clean. All loose bolts and nuts tight.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. water circulation pump motor greasing. It is ok. | Other | PUMP | |
| 15294 | 25 Aug 2020 | Scheduled Maintenance | The 3rd-floor side camera fitting is done. | Other | CAMERA | |
| 15295 | 24 Aug 2020 | Scheduled Maintenance | ALL CONVEYORS
BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. it's ok.
2. check panel board, clean, & tight all loose parts. clean and tight all loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly. its ok. | Other | RMHS CONVEYOR | |
| 15296 | 24 Aug 2020 | Scheduled Maintenance | ALL VIBRATORS
check Vibro feeders coil connection, its condition and ensure its working properly with adjusting its vibrations. BC 1 and BC 3 sides all Vibro feeders not in good condition. | Other | RMHS VIBRO FEEDER | |
| 15297 | 24 Aug 2020 | Scheduled Maintenance | ALL CONVEYORS
BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7
1. greasing of bearings.greasing is done.
2. lubrication of rollers and check conditions.its ok.
3. check belt status ( if damaged than inform and change) and also check tightness, speed. BC 6 and BC 7 are not in good condition we fitting fasteners and we fit separators for removing big stones from the drum.
4. gearbox oil level check and if not then fill as per requirement.it's ok.
5. check coupling and key ( if damaged than inform and change) and do the greasing.it's ok. BC 2 side coupling is not in good condition. we change it this week.
6. check the drum condition. it's ok.
7. check mounting frame welding condition.it's ok.
8. check rollers condition and if not good then change. we changer BC 6 side one return roller fall down we repaired it. | Other | RMHS CONVEYOR | |
| 15298 | 24 Aug 2020 | Scheduled Maintenance | 22 kW submersible pump motor testing with a transformer. | Other | SUBMERSIBLE PUMP | |
| 15299 | 24 Aug 2020 | Scheduled Maintenance | its pollution venturi side another pipeline giving and one 10 hp motor pump set fitting is done. | Other | POLLUTION 2 | |
| 15300 | 24 Aug 2020 | Scheduled Maintenance | 2 starter and motor connection giving at the pollution side. | Other | POLLUTION 2 | |