Maintenance Report
Search Filter:
Showing 15,011-15,020 of 17,159 items.
| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 15011 | 25 Sep 2020 | Scheduled Maintenance | 1. by air pipe clean dust from all cylinders.clean but seal side small amount of fire coming. 2. check leakage of hydraulic oil. if it is then informed to HOD.no leakage. | Furnace I | ELECTRODE 1 | |
| 15012 | 25 Sep 2020 | Breakdown Maintenance | OFFICE SIDE SUBMERSIBLE PUMP SHAFT DAMAGED. WE CHANGE IT WITH 3 HP SINGLE PHASE MOTOR. | Other | SUBMERSIBLE PUMP | |
| 15013 | 25 Sep 2020 | Scheduled Maintenance | CONTAINER TOP SIDE CAMERA FITTING IS DONE. | Other | CAMERA | |
| 15014 | 24 Sep 2020 | Scheduled Maintenance | CHIPPING YARD E.O.T. CRANE 2 LT. 1. check coupling, shaft, and pedestal bearing condition and do the greasing. greasing is done. it is ok. 2. check the gearbox oil level, leakage, and fill if required. no leakage but we fill grease. 3. check all fasteners and mounting bolts. it is ok. 4. check frame welding conditions. it is ok. 5. check end traveling gears condition and do the greasing. CT. 1. check coupling, shaft, and pedestal bearing condition and do the greasing. greasing is done. it is ok. 2. check the gearbox oil level, leakage, and fill if required. no leakage but we fill grease. 3. check all fasteners and mounting bolts. it is ok. 4. check frame welding conditions. it is ok. 5. check end traveling gears condition and do the greasing.it is ok. greasing is done. HT. 1. check rope drum, hook, rope condition. greasing of rope. greasing is done. we found that it is damage. we open and repaired. 2. check the thruster drum condition and its brake tightness. no thruster. 3. check all fasteners and mounting bolts. It is ok. 4. check frame welding conditions.it is ok. | Other | CHIPPING YARD CRANE NO. 2 | |
| 15015 | 24 Sep 2020 | Scheduled Maintenance | TELPHER FOR F1 1. checking the bearing, rollers condition, and do lubrication. checked it is ok. 2. checking frames welding condition.it is ok. 3. checking cotter pin and its failure condition. it is ok. | Other | TELPHER (FURNACE 1) | |
| 15016 | 24 Sep 2020 | Scheduled Maintenance | TELPHER FOR F2 1. checking the bearing, rollers condition, and do lubrication. checked it is ok. 2. checking frames welding condition.it is ok. 3. checking cotter pin and its failure condition. it is ok. | Other | TELPHER ( FURNACE 2) | |
| 15017 | 24 Sep 2020 | Scheduled Maintenance | POLLUTION ID FANS (Furnace 1) 1. open cover and clean dust.clean and balancing is done. tight nut bolts. 2. check the balancing of impeller and vibration isolation.it is ok. 3. check v belts condition and inform if it's on critical stage.it is ok. 4. check foundation bolts and nuts of Plummer blocks.it is ok. 5. greasing the Plummer blocks.greasing is done. 6. check the duct condition and remove dust from the duct. 7. check stack condition and check its temperature. it is ok. | Other | POLLUTION 1 | |
| 15018 | 24 Sep 2020 | Scheduled Maintenance | POLLUTION ID FANS FOR (Furnace 2) 1. open cover and clean dust.clean and balancing is done. tight nut bolts. 2. check the balancing of impeller and vibration isolation.it is ok. 3. check v belts condition and inform if it's on critical stage.it is ok. 4. check foundation bolts and nuts of Plummer blocks.it is ok. 5. greasing the Plummer blocks.greasing is done. 6. check the duct condition and remove dust from the duct. 7. check stack condition and check its temperature. it is ok. | Other | POLLUTION 2 | |
| 15019 | 24 Sep 2020 | Scheduled Maintenance | CHIPPING YARD E.O.T. CRANE 2 bus bar line is ok. LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. checked. it is ok. 2. check panel board, clean, & tight all loose parts. clean and tight loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly.it is ok. working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. checked. it is ok. 2. check panel board, clean, & tight all loose parts. clean and tight loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly.it is ok. working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. checked. it is ok. 2. check panel board, clean, & tight all loose parts. clean and tight loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly.it is ok. working properly. | Other | CHIPPING YARD CRANE NO. 2 | |
| 15020 | 24 Sep 2020 | Scheduled Maintenance | TELPHER FOR F1 1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform. motor condition checked. it is ok. 2. check panel board, clean, & tight all loose parts. clean and tight all loose parts. 3. all parts clean by hand blower. | Other | TELPHER (FURNACE 1) | |