Maintenance Report
Search Filter:
Showing 14,981-14,990 of 17,159 items.
| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 14981 | 28 Sep 2020 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE MECHANICAL TEA, FIX GEARBOX WE GIVING MOTOR CONNECTION. LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | TAPPING SEC. CRANE NO. 1 | |
| 14982 | 28 Sep 2020 | Scheduled Maintenance | ALL CONVEYORS BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. it's ok. 2. check panel board, clean, & tight all loose parts. clean and tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. its ok. | Other | RMHS CONVEYOR | |
| 14983 | 28 Sep 2020 | Scheduled Maintenance | ALL VIBRATORS check Vibro feeder coil connection, its condition, and ensure its working properly with adjusting its vibrations.no 2 discharge Vibro feeder coil changed. | Other | RMHS VIBRO FEEDER | |
| 14984 | 28 Sep 2020 | Scheduled Maintenance | ALL CONVEYORS BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7 1. greasing of bearings.grease is already there. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed.BC 1, BC 6, BC 5, BC 4, BC 3, repairs are done. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing.BC 2, BC 6 COUPLING CHANGING NEXT TIME. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. 6. check the drum condition. | Other | RMHS CONVEYOR | |
| 14985 | 28 Sep 2020 | Scheduled Maintenance | for washing plants we making one vibrator frame. we need to fit the new vibrator. | Other | VIBRATOR SCREEN MACHINE | |
| 14986 | 27 Sep 2020 | Breakdown Maintenance | its electrode 2 cooling blowers changed. now it's working. | Furnace II | ELECTRODE 2 | |
| 14987 | 27 Sep 2020 | Breakdown Maintenance | its electrode 2 cooling blower changed. now its ok. | Other | ELECTRODE 2 | |
| 14988 | 26 Sep 2020 | Scheduled Maintenance | TILTING HOPPER 1. greasing all bushes. 2.hydraulic pump and motor coupling. It's ok. 3. checking the hydraulic oil level and if not then fill. it's ok. The oil level is good. 4. check hopper welding sections. we found one crack at the hydraulic side. we weld it. now its ok. CONVEYOR NO 1 1. greasing of bearings. 2. lubrication of rollers and check conditions. The check is done. 3. check belt status ( if damaged than inform and change) and also check tightness, speed.its not ok. We mount some conveyor pieces and fasteners. 4. gearbox oil level check and if not then fill as per requirement.it's ok. 5. check coupling and key ( if damaged than inform and change) and do the greasing. it's ok. 6. check the drum condition. It's ok. 7. check mounting frame welding condition. it's ok. 8. check rollers condition and if not good then change. CRUSHER 1. check the crusher foundation.it's ok. 2. check V belts condition.it's ok. good in condition. 3. do greasing. greasing in the bearing is done. 4. check spring rod condition and the gap between plates.it's ok. 5. crusher side we making one cover. 5. crusher plate welding is done. VIBRATOR 1. check the spring condition. it is ok. 2. check V belts condition. it's ok. 3. check vibrations if not good then adjust. it's ok. 4. check the frame welding condition. it's ok. 5. Greasing of bearing is done. 6. vibrator frame and motor frame welding are done. ROLLER 1. check roller speed.it's ok. 2.greasing of bearings. 3.gearbox oil level check and if not then fill as per requirement.it's ok. 4. check coupling and key ( if damaged than inform and change) and do the greasing. it's ok. 5. check the drum condition. it's ok. 6. check the mounting frame welding condition. it's ok. 7. mesh is in good condition. 8. its belt condition not good it's needed to change next time. DISCHARGE CONVEYOR 1. greasing of bearings.greasing is done. 2. lubrication of rollers and check conditions.its ok. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. its ok. we repair the conveyor. 4. gearbox oil level check and if not then fill as per requirement. its ok.filling grease is done. 5. check coupling and key ( if damaged than inform and change) and do the greasing. it's ok. 6. check the drum condition. 7. check mounting frame welding condition. it's ok. 8. check rollers condition and if not good then change. | Other | WASHING PLANT | |
| 14989 | 26 Sep 2020 | Scheduled Maintenance | WASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. Check it is ok. 2. check panel board, clean, & tight all loose parts. Clean and tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. It's ok. 5. check the high mast lights also.its ok | Other | WASHING PLANT | |
| 14990 | 25 Sep 2020 | Scheduled Maintenance | F1- ELECTRODE BLOWER 1 SEAL COOLING BLOWER 1, 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.it is ok. 2. check panel board, clean, & tight all loose parts.clean and tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 1 | |