| 14591 | 08 Nov 2020 | Breakdown Shutdown | It's contact clamp NO. A3 has leakage. We try to fix it but the leakage is from inside. So we change the contact clamp. Now.its ok. | Furnace II | ELECTRODE 1 | |
| 14592 | 07 Nov 2020 | Scheduled Maintenance | No maintenance because all guys working in furnace side.
TILTING HOPPER
1. greasing all bushes.
2.hydraulic pump and motor coupling.
3. checking the hydraulic oil level and if not then fill.
4. check hopper welding sections.
CONVEYOR NO 1
1. greasing of bearings.
2. lubrication of rollers and check conditions.
3. check belt status ( if damaged than inform and change) and also check tightness, speed.
4. gearbox oil level check and if not then fill as per requirement.
5. check coupling and key ( if damaged than inform and change) and do the greasing.
6. check the drum condition.
7. check mounting frame welding condition.
8. check rollers condition and if not good then change.
CRUSHER
1. check the crusher foundation.
2. check V belts condition.
3. do greasing.
4. check spring rod condition and gap between plates.
VIBRATOR
1. check the spring condition.
2. check V belts condition.
3. check vibrations if not good then adjust.
4. check the frame welding condition.
ROLLER
1. check roller speed.
2.greasing of bearings.
3.gearbox oil level check and if not then fill as per requirement.
4. check coupling and key ( if damaged than inform and change) and do the greasing.
5. check the drum condition.
6. check the mounting frame welding condition.
DISCHARGE CONVEYOR
1. greasing of bearings.
2. lubrication of rollers and check conditions.
3. check belt status ( if damaged than inform and change) and also check tightness, speed.
4. gearbox oil level check and if not then fill as per requirement.
5. check coupling and key ( if damaged than inform and change) and do the greasing.
6. check the drum condition.
7. check mounting frame welding condition.
8. check rollers condition and if not good then change. | Other | WASHING PLANT | |
| 14593 | 07 Nov 2020 | Scheduled Maintenance | WASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.
5. check the high mast lights also. | Other | WASHING PLANT | |
| 14594 | 07 Nov 2020 | Breakdown Maintenance | It's coupling is damaged. We weld it. It's needed to be change. | Other | RMHS SHUTTLE CONVEYOR ( BELT CONVEYOR NO. 2) | |
| 14595 | 06 Nov 2020 | Scheduled Maintenance | 1. check the water manifold line, T section, and valves. All valves are ok.
2. check leakage of hose pipes. | Furnace I | WATER MAINEFOLD | |
| 14596 | 06 Nov 2020 | Scheduled Maintenance | 1. check the water manifold line, T section, and valves. All valve are working. No leakage.
2. check leakage of hose pipes.hose pipes are ok. | Furnace II | WATER MAINEFOLD | |
| 14597 | 06 Nov 2020 | Scheduled Maintenance | 1. by air pipe clean dust from all cylinders.Clean.
2. check leakage of hydraulic oil. if it is then informed to HOD.no leakage. | Furnace I | ELECTRODE 2 | |
| 14598 | 06 Nov 2020 | Scheduled Maintenance | 1. by air pipe clean dust from all cylinders.clean.
2. check leakage of hydraulic oil. if it is then informed to HOD.no leakage. | Furnace I | ELECTRODE 3 | |
| 14599 | 06 Nov 2020 | Scheduled Maintenance | 1. by air pipe clean dust from all cylinders.clean.
2. check leakage of hydraulic oil. if it is then informed to HOD.no leakage. | Furnace I | ELECTRODE 1 | |
| 14600 | 06 Nov 2020 | Breakdown Maintenance | It's plate coming out. It's mounting work is is done. now its ok. | Other | CRUSHER ( WASHING PLANT) | |