1435105 Dec 2020Scheduled MaintenanceWASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.
5. check the high mast lights also.
OtherWASHING PLANT
1435204 Dec 2020Scheduled Maintenance1. by air pipe clean dust from all cylinders. its ok.
2. check leakage of hydraulic oil. if it is then informed to HOD. small lekage in one slipping cylinder.
Furnace IELECTRODE 3
1435304 Dec 2020Scheduled Maintenance1. by air pipe clean dust from all cylinders. its ok.
2. check leakage of hydraulic oil. if it is then informed to HOD.
Furnace IELECTRODE 1
1435404 Dec 2020Breakdown Shutdownits electrode 1
3 contact clamps tie rod is going red. when we checking insulation we found that 5 tie rod and all clamps insulation is damaged. we change all insulations.
it's electrode 2 B1 clamp tie rod also damaged. we repaired with replacing new tie rod. now it's ok.
Furnace IIELECTRODE 1
1435504 Dec 2020Scheduled MaintenanceF1- ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.

Furnace IELECTRODE 1
1435604 Dec 2020Scheduled MaintenanceF1- ELECTRODE BLOWER 2

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
Furnace IELECTRODE 2
1435704 Dec 2020Scheduled MaintenanceF1- ELECTRODE BLOWER 3

1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.

Furnace IELECTRODE 3
1435804 Dec 2020Scheduled MaintenanceFURNACE 1

1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.

Furnace IHYDRAULIC POWER PACK NO. 1
1435904 Dec 2020Scheduled MaintenanceFURNACE 1

1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
4. check solenoid valves.
Furnace IHYDRAULIC POWER PACK NO. 2
1436004 Dec 2020Scheduled Maintenance ELECTRODE BLOWER 1
SEAL COOLING BLOWER 1,
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform.
2. check panel board, clean, & tight all loose parts.
3. all parts clean by hand blower.
Furnace IIELECTRODE 1