Maintenance Report
Search Filter:
Showing 13,881-13,890 of 17,159 items.
| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 13881 | 01 Feb 2021 | Other | We are making one foundation frame for the vibrator machine which will use for washing slag. its testing is done. We are adding some additional features on it. It's is ready. Fabrication work is complete. Testing successfully. | Other | VIBRATOR SCREEN MACHINE | |
| 13882 | 30 Jan 2021 | Scheduled Maintenance | Washing is breakdown. TILTING HOPPER 1. greasing all bushes. 2.hydraulic pump and motor coupling. 3. checking the hydraulic oil level and if not then fill. 4. check hopper welding sections. CONVEYOR NO 1 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. CRUSHER 1. check the crusher foundation. 2. check V belts condition. 3. do greasing. 4. check spring rod condition and gap between plates. VIBRATOR 1. check the spring condition. 2. check V belts condition. 3. check vibrations if not good then adjust. 4. check the frame welding condition. ROLLER 1. check roller speed. 2.greasing of bearings. 3.gearbox oil level check and if not then fill as per requirement. 4. check coupling and key ( if damaged than inform and change) and do the greasing. 5. check the drum condition. 6. check the mounting frame welding condition. DISCHARGE CONVEYOR 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. | Other | WASHING PLANT | |
| 13883 | 30 Jan 2021 | Scheduled Maintenance | WASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP(Replacement done) 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. 5. check the high mast lights also. | Other | WASHING PLANT | |
| 13884 | 30 Jan 2021 | Breakdown Maintenance | It's motor foundation is broken. Because of the chipping yard guys not use properly they using it to pull the metal trolly from tapping section. We repair it using cast-iron welding rod.now it's ok. | Other | CHIPPING YARD CRANE NO. 1 | |
| 13885 | 29 Jan 2021 | Scheduled Maintenance | F1- ELECTRODE BLOWER 1 SEAL COOLING BLOWER 1, 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 1 | |
| 13886 | 29 Jan 2021 | Scheduled Maintenance | F1- ELECTRODE BLOWER 2 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 2 | |
| 13887 | 29 Jan 2021 | Scheduled Maintenance | F1- ELECTRODE BLOWER 3 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. | Furnace I | ELECTRODE 3 | |
| 13888 | 29 Jan 2021 | Scheduled Maintenance | FURNACE 1 1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check solenoid valves. | Furnace I | HYDRAULIC POWER PACK NO. 1 | |
| 13889 | 29 Jan 2021 | Scheduled Maintenance | FURNACE 1 1.check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check solenoid valves. | Furnace I | HYDRAULIC POWER PACK NO. 2 | |
| 13890 | 29 Jan 2021 | Scheduled Maintenance | ELECTRODE BLOWER 1 SEAL COOLING BLOWER 1, 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. | Furnace II | ELECTRODE 1 | |