Maintenance Report
Search Filter:
Showing 13,301-13,310 of 17,159 items.
| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 13301 | 14 Apr 2021 | Breakdown Shutdown | its B6 clamp has water leakage from cup. we brazing it. now its ok. | Furnace II | ELECTRODE 2 | |
| 13302 | 14 Apr 2021 | Breakdown Maintenance | It's completely out from the chipping yard to do some changes in design. we change its L.T. shaft completely with solid. now its ok. CHIPPING YARD E.O.T. CRANE 1 LT. 1. check coupling, shaft, and pedestal bearing condition and do the greasing. 2. check the gearbox oil level, leakage, and fill if required. 3. check all fasteners and mounting bolts. 4. check frame welding conditions. 5. check end traveling gears condition and do the greasing. CT. 1. check coupling, shaft, and pedestal bearing condition and do the greasing. 2. check the gearbox oil level, leakage, and fill if required. 3. check all fasteners and mounting bolts. 4. check frame welding conditions. 5. check end traveling gears condition and do the greasing. HT. 1. check rope drum, hook, rope condition. greasing of rope. 2. check the thruster drum condition and its brake tightness. 3. check all fasteners and mounting bolts. 4. check frame welding conditions. | Other | CHIPPING YARD CRANE NO. 1 | |
| 13303 | 13 Apr 2021 | Scheduled Maintenance | WATER CIRCULATION PUMP 1,2,3, FURNACE 1 GRANULATION PUMP 1,2 SUBMERSIBLE PUMP 1,2, POLLUTION WATER PUMP NO 1 FURNACE 2 GRANULATION PUMP 1,2, POLLUTION WATER PUMP NO 1, OFFICE SUBMERSIBLE PUMP 1, WASHING PLANT SUBMERSIBLE PUMP 1 1. check the pump condition and check discharge. 2. check coupling condition, alignment, and do greasing. 3. check pipelines and valve's condition. 4. check cooling towers nozzles condition. | Other | PUMP | |
| 13304 | 13 Apr 2021 | Scheduled Maintenance | F1- GRANULATION MOTOR 1,2 WATER CIRCULATION PUMP MOTOR 1,2,3, SUBMERSIBLE PUMP MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1 F2- GRANULATION MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1, OFFICE SUBMERSIBLE PUMP MOTOR 1, WASHING PLANT SUBMERSIBLE PUMP MOTOR1 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. water circulation pump motor greasing. | Other | PUMP | |
| 13305 | 12 Apr 2021 | Scheduled Maintenance | ALL CONVEYORS BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | RMHS CONVEYOR | |
| 13306 | 12 Apr 2021 | Scheduled Maintenance | ALL VIBRATORS check Vibro feeders coil connection, its condition and ensure its working properly with adjusting its vibrations. | Other | RMHS VIBRO FEEDER | |
| 13307 | 12 Apr 2021 | Scheduled Maintenance | ALL CONVEYORS BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. | Other | RMHS CONVEYOR | |
| 13308 | 11 Apr 2021 | Breakdown Shutdown | It's electrode 1 is broken. Length 1.2 mtr We switch off furnace and removing it with chain block. We also weld some pressure ring leakage form electrode hanger side. | Furnace I | ELECTRODE 1 | |
| 13309 | 10 Apr 2021 | Scheduled Maintenance | TILTING HOPPER 1. greasing all bushes. 2.hydraulic pump and motor coupling. 3. checking the hydraulic oil level and if not then fill. 4. check hopper welding sections. CONVEYOR NO 1 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. CRUSHER 1. check the crusher foundation. 2. check V belts condition. 3. do greasing. 4. check spring rod condition and gap between plates. VIBRATOR 1. check the spring condition. 2. check V belts condition. 3. check vibrations if not good then adjust. 4. check the frame welding condition. ROLLER 1. check roller speed. 2.greasing of bearings. 3.gearbox oil level check and if not then fill as per requirement. 4. check coupling and key ( if damaged than inform and change) and do the greasing. 5. check the drum condition. 6. check the mounting frame welding condition. DISCHARGE CONVEYOR 1. greasing of bearings. 2. lubrication of rollers and check conditions. 3. check belt status ( if damaged than inform and change) and also check tightness, speed. 4. gearbox oil level check and if not then fill as per requirement. 5. check coupling and key ( if damaged than inform and change) and do the greasing. 6. check the drum condition. 7. check mounting frame welding condition. 8. check rollers condition and if not good then change. | Other | WASHING PLANT | |
| 13310 | 10 Apr 2021 | Scheduled Maintenance | WASHING PLANT TILTING HOPPER, CONVEYOR NO 1, CRUSHER, VIBRATOR, ROLLER, DISCHARGE CONVEYOR , WATER PUMP 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. 5. check the high mast lights also. | Other | WASHING PLANT | |