Maintenance Report
Search Filter:
Showing 11,921-11,930 of 17,159 items.
| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 11921 | 20 Oct 2021 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE 1 LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | TAPPING SEC. CRANE NO. 1 | |
| 11922 | 20 Oct 2021 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE 2 LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | TAPPING SEC. CRANE NO. 2 | |
| 11923 | 20 Oct 2021 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE 3 LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | TAPPING SEC. CRANE NO. 3 | |
| 11924 | 20 Oct 2021 | Scheduled Maintenance | 3RD FLOOR CARBON PASTE LIFTING CRANE LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | CARBON PASTE LIFTING CRANE | |
| 11925 | 20 Oct 2021 | Other | 3 NOS CONTECT CLAMPS REPAIRING IS DONE. | Other | CONTACT CLAMP (SPARE) | |
| 11926 | 19 Oct 2021 | Breakdown Maintenance | It's C.T. gear box inside pinion gear is damaged and completely finish we open it. We are arranging a new gear box fitting is done. Now it's running in good condition. | Other | TAPPING SEC. CRANE NO. 3 | |
| 11927 | 19 Oct 2021 | Scheduled Maintenance | WATER CIRCULATION PUMP 1,2,3, FURNACE 1 GRANULATION PUMP 1,2 SUBMERSIBLE PUMP 1,2, POLLUTION WATER PUMP NO 1 FURNACE 2 GRANULATION PUMP 1,2, POLLUTION WATER PUMP NO 1, OFFICE SUBMERSIBLE PUMP 1, WASHING PLANT SUBMERSIBLE PUMP 1 1. check the pump condition and check discharge. 2. check coupling condition, alignment, and do greasing. 3. check pipelines and valve's condition. 4. check cooling towers nozzles condition. | Other | PUMP | |
| 11928 | 19 Oct 2021 | Scheduled Maintenance | F1- GRANULATION MOTOR 1,2 WATER CIRCULATION PUMP MOTOR 1,2,3, SUBMERSIBLE PUMP MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1 F2- GRANULATION MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1, OFFICE SUBMERSIBLE PUMP MOTOR 1, WASHING PLANT SUBMERSIBLE PUMP MOTOR1 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. water circulation pump motor greasing. | Other | PUMP | |
| 11929 | 19 Oct 2021 | Breakdown Maintenance | It's bearing,plummer block and adapter sleeve is damaged. We replace it with new one. Bearing is 23224 Adapter sleeve is H2324 AND PLUMMER block is SN 524 | Other | POLLUTION 1, ID FAN NO. 2 | |
| 11930 | 18 Oct 2021 | Scheduled Maintenance | ALL CONVEYORS BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | RMHS CONVEYOR | |