Maintenance Report
Search Filter:
Showing 10,911-10,920 of 17,159 items.
| # | Date | Type | Details | Furnace | Equipment | Actions |
|---|---|---|---|---|---|---|
| 10911 | 23 Feb 2022 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE 2 LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | TAPPING SEC. CRANE NO. 2 | |
| 10912 | 23 Feb 2022 | Scheduled Maintenance | TAPPING SECTION E.O.T. CRANE 3 LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | TAPPING SEC. CRANE NO. 3 | |
| 10913 | 23 Feb 2022 | Scheduled Maintenance | 3RD FLOOR CARBON PASTE LIFTING CRANE LT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. CT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. HT. 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | CARBON PASTE LIFTING CRANE | |
| 10914 | 23 Feb 2022 | Breakdown Maintenance | its motor is burn. we fix new motor. now its ok. | Other | RMHS BELT CONVEYOR NO.6 | |
| 10915 | 23 Feb 2022 | Breakdown Maintenance | its pump nrv valve is leakage. we fix it now its ok. | Other | COOLING TOWER | |
| 10916 | 22 Feb 2022 | Other | 1200 mm dia pipe line fabrication work is in progress for f1 pollution. its flange fabrication work is done. we also keep BOTH container at required place. both id fan are connected and tested. duct pipe line connected to chimney. water pump line connection is done and tested. container strainers also fitted and tested. outlet water pipe line work is complete. pollution can start | Other | POLLUTION FUME SYSTEM | |
| 10917 | 22 Feb 2022 | Scheduled Maintenance | WATER CIRCULATION PUMP 1,2,3, FURNACE 1 GRANULATION PUMP 1,2 SUBMERSIBLE PUMP 1,2, POLLUTION WATER PUMP NO 1 FURNACE 2 GRANULATION PUMP 1,2, POLLUTION WATER PUMP NO 1, OFFICE SUBMERSIBLE PUMP 1, WASHING PLANT SUBMERSIBLE PUMP 1 1. check the pump condition and check discharge. 2. check coupling condition, alignment, and do greasing. 3. check pipelines and valve's condition. 4. check cooling towers nozzles condition. | Other | PUMP | |
| 10918 | 22 Feb 2022 | Scheduled Maintenance | F1- GRANULATION MOTOR 1,2 WATER CIRCULATION PUMP MOTOR 1,2,3, SUBMERSIBLE PUMP MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1 F2- GRANULATION MOTOR 1,2, POLLUTION WATER PUMP MOTOR NO 1, OFFICE SUBMERSIBLE PUMP MOTOR 1, WASHING PLANT SUBMERSIBLE PUMP MOTOR1 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. water circulation pump motor greasing. | Other | PUMP | |
| 10919 | 22 Feb 2022 | Other | protection shield fabrication and insulation drilling work is done. | Furnace II | FURNACE 2 | |
| 10920 | 21 Feb 2022 | Scheduled Maintenance | ALL CONVEYORS BC 1, BC 2, BC 3, BC 4, BC 5, BC 6, BC 7 1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. 2. check panel board, clean, & tight all loose parts. 3. all parts clean by hand blower. 4. check limit switches and its condition. ensure that all limit switches and wires working properly. | Other | RMHS CONVEYOR | |