Maintenance Details
| Date | 12 May 2020 |
|---|---|
| Start Time | 07:30:10 |
| End Time | 16:30:00 |
| Nature Of Maintenance | Mechanical |
| Equipment | PUMP |
| Type of Maintenance | Scheduled Maintenance |
| Details | WATER CIRCULATION PUMP 1,2,3, FURNACE 1 GRANULATION PUMP 1,2 SUBMERSIBLE PUMP 1,2, POLLUTION WATER PUMP NO 1 FURNACE 2 GRANULATION PUMP 1,2, POLLUTION WATER PUMP NO 1, OFFICE SUBMERSIBLE PUMP 1, WASHING PLANT SUBMERSIBLE PUMP 1 1. check the pump condition and check discharge.it is ok. We fit f1 pollution pump gland rope and now it is ok. 2. check coupling condition, alignment, and do greasing.it is ok. 3. check pipelines and valve's condition. 4. check cooling towers nozzles condition.it Is ok. |
| Remark | (not set) |
| Furnace | Other |
| Status | Completed |