Maintenance Details
| Date | 09 May 2020 |
|---|---|
| Start Time | 09:00:00 |
| End Time | 13:00:00 |
| Nature Of Maintenance | Electrical |
| Equipment | WEIGH BRIDGE |
| Type of Maintenance | Breakdown Maintenance |
| Details | It's servicing is done. All load cells bottom side and top side shaking balls also cleaned.we are changing 5 nos balls which are rusted. |
| Remark | (not set) |
| Furnace | Other |
| Status | Completed |