Maintenance Details
| Date | 22 Apr 2020 |
|---|---|
| Start Time | 07:30:35 |
| End Time | 16:30:35 |
| Nature Of Maintenance | Mechanical |
| Equipment | OTHERS |
| Type of Maintenance | Scheduled Maintenance |
| Details | TAPPING SECTION E.O.T. CRANE 1,2, AND 3RD FLOOR carbon paste lifting crane LT. 1. coupling, shaft, and pedestal bearing condition checked and greasing is done. 2. the gearbox oil level checked. No leakage. 3. checked all fasteners and mounting bolts. 4. checked frame welding conditions. 5. checked end traveling gears condition and do the greasing it is ok. CT. 1. coupling, shaft, and pedestal bearing condition checked and greasing is done. 2. checked the gearbox oil level. For crane no 2 ct gear box has leakage. 3. checked all fasteners and mounting bolts. 4. checked frame welding conditions. 5. checked end traveling gears condition and do the greasing. HT. 1. checked rope drum, hook, rope condition. 2. checked the thruster drum condition and its brake tightness. 3. checked all fasteners and mounting bolts. 4. checked frame welding conditions. |
| Remark | (not set) |
| Furnace | Other |
| Status | Completed |