Maintenance Details


Date21 Apr 2020
Start Time07:30:30
End Time16:30:30
Nature Of MaintenanceMechanical
EquipmentOTHERS
Type of MaintenanceScheduled Maintenance
DetailsWATER CIRCULATION PUMP 1
coupling checking and greasing are done. motor checking and greasing are done.

FURNACE 1
GRANULATION PUMP 1,2
SUBMERSIBLE PUMP 1,2,
POLLUTION WATER PUMP NO 1
we fit 2 nos rubber bush for protecting the motor from water leakage.
FURNACE 2
GRANULATION PUMP 1,2,
POLLUTION WATER PUMP NO 1,
OFFICE SUBMERSIBLE PUMP 1,
WASHING PLANT SUBMERSIBLE PUMP 1

1.pump condition and discharge checked.
2.coupling condition, alignment, and greasing done.
3.pipelines and valve's condition checked. it is ok.
4. check cooling towers nozzles condition. it is ok.
Remark(not set)
FurnaceOther
StatusCompleted