Furnace I

ShiftA
FurnaceFurnace I
Date01 Mar 2026
MWH37.5
MVAH43.5
PF0.86
Tap Change Reading87282
No of tap changing0
Paste Level - E14.6
Paste Level - E24.45
Paste Level - E34.5
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E10
Slipping - E250
Slipping - E30
CROSydney
Total No. of Batches15
Plant 66kv kvah(not set)
Shift InchargeAdinarayana