Maintenance Details
| Date | 06 Feb 2022 |
|---|---|
| Start Time | 06:00:40 |
| End Time | 03:00:00 |
| Nature Of Maintenance | Mechanical |
| Equipment | FURNACE 1 |
| Type of Maintenance | Scheduled Shutdown |
| Details | zesco shutdown Details pollution chimney duct line connection work is done. contact clamp suspension link 4 sets changed. E3 slipping cylinder changed. E3 & E1 pressuring pipe welding. E2 pressure ring hanger insulation done E3 protection shield to mental insulation hood center part welding hood part number 1,2 and 3 welding pump number 2 NRV repairing E1 contact clamp hose pipes changed transformer riser side 2 nos hose pipe changed. charging chute number 2 repairing E3 mantle lower waterline valve replacement hydraulic power pack oil leakage arrested |
| Remark | |
| Furnace | Furnace I |
| Status | Completed |