Furnace II

ShiftB
FurnaceFurnace II
Date29 Jun 2024
MWH36.7
MVAH44.4
PF0.82
Tap Change Reading60713
No of tap changing46
Paste Level - E15.25
Paste Level - E25.2
Paste Level - E35.25
Casing Fitting - E10
Casing Fitting - E21
Casing Fitting - E30
Slipping - E1150
Slipping - E2100
Slipping - E3150
CROEmmanuel
Total No. of Batches15
Plant 66kv kvah0
Shift InchargeRamesh