| Shift | A |
|---|---|
| Furnace | Furnace II |
| Date | 11 Jun 2024 |
| MWH | 42.5 |
| MVAH | 51.5 |
| PF | 0.82 |
| Tap Change Reading | 59985 |
| No of tap changing | 0 |
| Paste Level - E1 | 4.5 |
| Paste Level - E2 | 4.6 |
| Paste Level - E3 | 4.85 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 150 |
| Slipping - E2 | 50 |
| Slipping - E3 | 150 |
| CRO | Elisha |
| Total No. of Batches | 12 |
| Plant 66kv kvah | 0 |
| Shift Incharge | Donald |