Maintenance Details
| Date | 17 Dec 2021 |
|---|---|
| Start Time | 03:06:31 |
| End Time | 03:06:31 |
| Nature Of Maintenance | Mechanical |
| Equipment | CHARGING CHUTES |
| Type of Maintenance | Scheduled Maintenance |
| Details | 1.check solenoid valve condition and its pipe condition. 2.check pneumatic cylinders and air supply line. 3. check charging chute leakage. if it is than inform HOD. we checked all chutes are ok chute number 7 is coming out. we cut Falange today and start pipe making work. hydraulic leakage at hydraulic power pack side arrested today during shutdown. |
| Remark | |
| Furnace | Furnace I |
| Status | Completed |