Maintenance Details
| Date | 06 Jan 2022 |
|---|---|
| Start Time | 14:54:45 |
| End Time | 14:54:45 |
| Nature Of Maintenance | Mechanical |
| Equipment | NEW POLLUTION TANK |
| Type of Maintenance | Other |
| Details | 6 inch MS pipe fitting for pollution 1 is done tested. for pollution 2 in ONE DISCHARGE PIPE LINE IS DONE. we are done work for it. we are waiting for the required pumps. now all pump s are connected to the pipe line. |
| Remark | |
| Furnace | Other |
| Status | Completed |