Maintenance Details
| Date | 11 Dec 2021 |
|---|---|
| Start Time | 16:11:15 |
| End Time | 16:11:15 |
| Nature Of Maintenance | Mechanical |
| Equipment | NEW WASHING PLANT |
| Type of Maintenance | Other |
| Details | ITS FABRICATION WORK IS IN PROGRESS. ALL foundation columns are fabricated. tipper foundation is done. today we kept its foundation frame. welding is in progress. 1000 MM conveyor foundation is done. its frame also kept on top. crusher foundation work is in progress. log washer foundation and its fitting also done. discharge conveyor fitting is done. dust conveyor fitting is done. tomorrow we fitting conveyor belt ON BOTH SMALL CONVEYORS. big crusher foundation work is in progress. |
| Remark | |
| Furnace | Other |
| Status | On going |