Maintenance Details


Date11 Dec 2021
Start Time16:11:15
End Time16:11:15
Nature Of MaintenanceMechanical
EquipmentNEW WASHING PLANT
Type of MaintenanceOther
DetailsITS FABRICATION WORK IS IN PROGRESS.
ALL foundation columns are fabricated.
tipper foundation is done. today we kept its foundation frame. welding is in progress.
1000 MM conveyor foundation is done. its frame also kept on top.
crusher foundation work is in progress.
log washer foundation and its fitting also done.
discharge conveyor fitting is done.
dust conveyor fitting is done. tomorrow we fitting conveyor belt ON BOTH SMALL CONVEYORS.
big crusher foundation work is in progress.
Remark
FurnaceOther
StatusOn going