Maintenance Details


Date06 Nov 2021
Start Time08:00:05
End Time13:30:05
Nature Of MaintenanceMechanical
EquipmentFURNACE 2
Type of MaintenanceBreakdown Shutdown
DetailsZESCO POWER BREKDOWN SHUTDOWN
ELECTRODE 2
contact clamp B6, suspension link, fork repaired and change with insulation.

ELECTRODE 3
contact clamp C3, suspension link, fork repaired and change with insulation.
ALSO SEAL BOX SIDE 3MTR 100 mm dia asbestos rope changed.

After that we welding charging chute.
Both hydraulic power packs leakage arrest.
Remark
FurnaceFurnace II
StatusCompleted