Maintenance Details
| Date | 22 Feb 2022 |
|---|---|
| Start Time | 11:27:50 |
| End Time | 11:27:50 |
| Nature Of Maintenance | Mechanical |
| Equipment | POLLUTION FUME SYSTEM |
| Type of Maintenance | Other |
| Details | 1200 mm dia pipe line fabrication work is in progress for f1 pollution. its flange fabrication work is done. we also keep BOTH container at required place. both id fan are connected and tested. duct pipe line connected to chimney. water pump line connection is done and tested. container strainers also fitted and tested. outlet water pipe line work is complete. pollution can start |
| Remark | |
| Furnace | Other |
| Status | Completed |