Maintenance Details
| Date | 10 Oct 2021 |
|---|---|
| Start Time | 09:10:25 |
| End Time | 18:10:25 |
| Nature Of Maintenance | Mechanical |
| Equipment | FURNACE 1 |
| Type of Maintenance | Scheduled Shutdown |
| Details | zesco shutdown Electrode 1 Full welding of pipe line with changing pipe line of pressure ring from P1 TO P2 ALL CLAMP insulation checked and changed. ELECTORDE 2 All clamp insulation checked and changed. Electrode 3 All clamp insulation checked and changed. |
| Remark | |
| Furnace | Furnace I |
| Status | Completed |