| Date | 30 Sep 2021 |
|---|---|
| Start Time | 08:00:15 |
| End Time | 20:00:15 |
| Nature Of Maintenance | Mechanical |
| Equipment | FURNACE 2 |
| Type of Maintenance | Scheduled Shutdown |
| Details | Protection shield full welding is done. Electrode 2 B5 MAINTEL LOWER side full bus tube open and leakage arrest. Than it's B5 content clamp changed. Bus tube side upper and lower full breaking with contact clmap breazzing is done. It's Pressure ring lifting with 1nos fork changed with full welding. 2nd floor Seal box electrode 3 Air pipe line changed. |
| Remark | |
| Furnace | Furnace II |
| Status | Completed |