Furnace I

ShiftB
FurnaceFurnace I
Date23 Apr 2023
MWH34.7
MVAH43.9
PF0.78
Tap Change Reading69847
No of tap changing12
Paste Level - E14
Paste Level - E24.05
Paste Level - E34.1
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E1100
Slipping - E2100
Slipping - E3100
CROKelvin musonda
Total No. of Batches11
Plant 66kv kvah(not set)
Shift InchargeVishnu