Furnace I

ShiftB
FurnaceFurnace I
Date21 Apr 2023
MWH21.8
MVAH26.3
PF0.82
Tap Change Reading69624
No of tap changing41
Paste Level - E14.7
Paste Level - E24.5
Paste Level - E34.6
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E1150
Slipping - E20
Slipping - E30
CROLaston
Total No. of Batches7
Plant 66kv kvah(not set)
Shift InchargeVishnu