Maintenance Details
| Date | 07 Apr 2021 |
|---|---|
| Start Time | 05:20:00 |
| End Time | 06:40:00 |
| Nature Of Maintenance | Mechanical |
| Equipment | ELECTRODE 2 |
| Type of Maintenance | Breakdown Shutdown |
| Details | It's electrode 2 and 3 have sparking. We check that it's B1 and BE clamp pressure ring bolts and nut are too much going inside. So we open it and changing all spring set, bolt and but. After that we tight it. It's C1 and C2 clamp also have heavy water leakage. But we fill pulp to stop it. now itsok. |
| Remark | |
| Furnace | Furnace I |
| Status | Completed |