Maintenance Details


Date20 Mar 2021
Start Time00:00:10
End Time04:00:00
Nature Of MaintenanceMechanical
EquipmentFURNACE 2
Type of MaintenanceScheduled Shutdown
DetailsDay 1
All contact clamps of electrode 1,2 and 3 with pressure ring bolts nuts and springs out.
Electrode 3 damaged protection shield cutting and out.
It's C2 clamp bus bar cutting and out.
Electrode 1, 2 and 3 side all new contect clamps fitting is done.we changing all tie rods side insulation and some tie rods. Pressure ring side all spring changed.

Day 2
Some remaining contact clamps for electrode 3 fitting is done. All pressure ring bolts tighting and breazing is done.

Electrode 3 side clamp C2 mantle lower leakage repaired.after that there side insulation also fitting is done. Upper mantle side 4 nos insulation fitting is done.
Than. Bus bar line fitting with brazing.

Protection shield fitting is done with matching and full welding.

Electrode 2 side protection shield welding is done.

Water manifold side 10 nos new valve fitting is done.

All 3 electrode upper mantle seal rope changed.

Seal box of electrode 3 side new rope fitting is done.its water hose pipe also changed.

Furnace all Charing chutes direction giving and welding is done.
Remark
FurnaceFurnace II
StatusCompleted