Maintenance Details


Date26 Nov 2020
Start Time07:30:30
End Time16:30:30
Nature Of MaintenanceMechanical
EquipmentTAPPING SEC. CRANE NO. 1
Type of MaintenanceScheduled Maintenance
Detailsits L.T. SIDE WHEEL NO. 2 bearing is damage. we park it on the tapping side because its H.T. and c.t. is working. its wheel preparation is finish. we fit it on 6014 bearing 2 nos.
now its working.
TAPPING SECTION E.O.T. CRANE 1

LT.
1. check coupling, shaft, and pedestal bearing condition and do the greasing.
2. check the gearbox oil level, leakage, and fill if required.
3. check all fasteners and mounting bolts.
4. check frame welding conditions.
5. check end traveling gears condition and do the greasing.

CT.
1. check coupling, shaft, and pedestal bearing condition and do the greasing.
2. check the gearbox oil level, leakage, and fill if required.
3. check all fasteners and mounting bolts.
4. check frame welding conditions.
5. check end traveling gears condition and do the greasing.

HT.
1. check rope drum, hook, rope condition. greasing of rope.
2. check the thruster drum condition and its brake tightness.
3. check all fasteners and mounting bolts.
4. check frame welding conditions.
Remark
FurnaceOther
StatusCompleted