SAFAL/P/IRON ORE/02/2026/43
| Contract Number | SAFAL/P/IRON ORE/02/2026/43 |
| Contract Date | 20 Feb 2026 |
| Type | Purchase |
| Supplier Name | KEMOSE MINING LIMITED |
| Description of Goods | Iron Ore |
| Grade | N/A |
| Size | 10-100MM |
| Specifications | Fe +65% |
| Quantity | 30 |
| Weight Unit | Metric Tonne |
| Destination | SAFAL PLANT KANONA |
| Rate | 650 |
| Currency | Zambian Kwacha |
| VAT % | 0 |
| Mode/Terms of Payment | 100% Payment after receiving the quantity and upon testing at our lab. |
| Terms of Delivery | Delivered at our Kanona Plant |
| Delivery Period | Immediate |
| Dispatch Through | Seller's Hired trucks |
| Lot Number | KEMOSE MINING IRON 2026 |
| Remark | Material to be supplied as per PO Specs only. If any variation observed at buyer's lab, material can be rejected |
| Other Reference(s) | |
|---|
Showing 1-1 of 1 item.
| # | Supply Date | Supplier Name | Item | Grade (%) | Inward Quantity |
| 1 | 19 Feb 2026 | KEMOSE MINING LIMITED | Iron Ore | N/A | 23.04 |
Total Supply: 23.04