SAFAL/P/MANGANESE ORE/07/2023/23


Contract NumberSAFAL/P/MANGANESE ORE/07/2023/23
Contract Date25 Jul 2023
TypePurchase
Supplier NameAMIZO POWER ENGINEERS LTD
Description of Goods Manganese Ore
GradeHigh (44% - 50%)
Size10-120MM(MIN 90%)
SpecificationsSPECIFICATIONS REQUIREMENT- MN 48% MIN. PHOSHPHORUS SHOULD BE LESS THAN 0.13 % ,SILICA SHOULD BE MAX 8%,FE AND AL203 % SHOULD BE LESS THAN 5%.
Quantity500
Weight UnitMetric Tonne
DestinationSAFAL PLANT KANONA
Rate95
CurrencyUS Dollar
VAT %16
Mode/Terms of PaymentUpon delivery at SAFAL plant and testing of the material
Terms of DeliveryEX MINE MATERIAL LOADED ON TRUCKS.
Delivery PeriodIMMEDIATE
Dispatch ThroughBUYER HIRED TRUCKS
Lot NumberAmizo Power Mn ore FY 23
Remark1 ALL TRUCKS SHOULD ACCOMPANY MINING LICENCE COPY,COUNCIL RECEIPTS AND MANGANESE CLERANCE. 2 DOCUMENTS CHARGES LIKE WEIGHBRIDGE COST,COUNCIL FEES COST AND TRUCK LEVY WILL BE PAID BY SAFAL IN MANSA. 3 AN ADVANCE AMOUNT OF 20000 USD TO BE PAID BEFORE COMMENCEMENT OF SUPPLY BY SAFAL AGAINST THE SUBJECT ORDER OF 500 MT AND ON THE COMPLETION OF ORDER ,DEPOSIT AMOUNT TO BE REFUNDED OR CARRIED FORWARD FOR NEXT ORDER.
Other Reference(s)PRICE IS INCLUDING MRT.CERTIFICATE TO BE PROVIDED EVERY MONTH END BY THE SUPPLIER.
Showing 1-12 of 12 items.
#Supply DateSupplier NameItemGrade (%)Inward Quantity
131 Jul 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)46
201 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)40.9
301 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)35.48
401 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)39.88
504 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)39.74
604 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)32.28
709 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)46.58
809 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)46.86
910 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)46.48
1012 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)41.18
1113 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)47.02
1215 Aug 2023AMIZO POWER ENGINEERS LTDManganese OreHigh (44% - 50%)45.18

Total Supply: 507.58