Furnace I

ShiftB
FurnaceFurnace I
Date14 Dec 2021
MWH39.1
MVAH46.2
PF0.84
Tap Change Reading6253
No of tap changing16
Paste Level - E14.5
Paste Level - E24.25
Paste Level - E34.2
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E2100
Slipping - E350
CROHardson
Total No. of Batches54
Plant 66kv kvah(not set)
Shift InchargeSydney