SAFAL/P/MN ORE/08.03/2022


Contract NumberSAFAL/P/MN ORE/08.03/2022
Contract Date08 Aug 2022
TypePurchase
Supplier NameSanjay and Krishna Investments Ltd
Description of Goods Manganese Ore
GradeHigh (44% - 50%)
Size10-100 MM (90% Min)
SpecificationsMN MIN 48% AS PER THE PO. MN FROM 44 TO 47.9 GRTADE PRICE WILL BE CONSIDERED AS 126 DOLLAR DELIVERED.
Quantity500
Weight UnitMetric Tonne
DestinationSAFAL PLANT KANONA
Rate146
CurrencyUS Dollar
VAT %16
Mode/Terms of PaymentUpon delivery at SAFAL plant and testing of the material
Terms of DeliveryDELIVERED KANONA PLANT SAFAL
Delivery PeriodIMMEDIATE
Dispatch ThroughSUPPLIER HIRED TRUCKS
Lot NumberSanjay and Krishna Investment Ltd-Mn Ore
RemarkTRUCKS SHOULD ACCOMPANY COUNCIL RECIPTS AND POLICE CLERANCE AND LICENCE COPY.
Other Reference(s)PRICE IS INCLUDING MINERAL ROYALTY.
Showing 1-1 of 1 item.
#Supply DateSupplier NameItemGrade (%)Inward Quantity
112 Aug 2022Sanjay and Krishna Investments LtdManganese OreHigh (44% - 50%)46.58

Total Supply: 46.58