Maintenance Details
| Date | 07 Aug 2020 |
|---|---|
| Start Time | 07:30:01 |
| End Time | 08:30:01 |
| Nature Of Maintenance | Mechanical |
| Equipment | ELECTRODE 3 |
| Type of Maintenance | Scheduled Maintenance |
| Details | 1. by air pipe clean dust from all cylinders.it's one slipping cylinder has leakage. we change it in the next scheduled shutdown. 2. check leakage of hydraulic oil. if it is then informed to HOD. 3. its protection shield is finished completely. we making it. its work is in progress. |
| Remark | |
| Furnace | Furnace I |
| Status | Completed |