SAFAL/P/STEAM COAL/07.07/2021
| Contract Number | SAFAL/P/STEAM COAL/07.07/2021 |
| Contract Date | 08 Jul 2021 |
| Type | Purchase |
| Supplier Name | Maamba Energy Limited |
| Description of Goods | Steam Coal |
| Grade | N/A |
| Size | 20-35MM |
| Specifications | FC : 60% Min |
| Quantity | 500 |
| Weight Unit | Metric Tonne |
| Destination | SAFAL Plant, Kanona |
| Rate | 82 |
| Currency | US Dollar |
| VAT % | 16 |
| Mode/Terms of Payment | 100% Advance |
| Terms of Delivery | Ex Works Maamba |
| Delivery Period | Immediate |
| Dispatch Through | Buyer hired trucks |
| Lot Number | Maamba Collieries- 10-35 (nut's) |
| Remark | |
| Other Reference(s) | |
|---|
Showing 1-15 of 15 items.
| # | Supply Date | Supplier Name | Item | Grade (%) | Inward Quantity |
| 1 | 12 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 30.335 |
| 2 | 14 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 31.14 |
| 3 | 14 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 31.365 |
| 4 | 14 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 33.755 |
| 5 | 14 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 33.475 |
| 6 | 14 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 32.54 |
| 7 | 21 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 33.65 |
| 8 | 22 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 33.115 |
| 9 | 23 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 29.4 |
| 10 | 23 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 32.26 |
| 11 | 24 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 31.5 |
| 12 | 24 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 32.795 |
| 13 | 24 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 33.25 |
| 14 | 25 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 31.365 |
| 15 | 25 Jul 2021 | Maamba Energy Limited | Steam Coal | N/A | 30.655 |
Total Supply: 480.6