Maintenance Details


Date09 Jul 2020
Start Time07:30:01
End Time08:30:01
Nature Of MaintenanceElectrical
EquipmentCHIPPING YARD CRANE NO. 2
Type of MaintenanceScheduled Maintenance
DetailsCHIPPING YARD E.O.T. CRANE 2

LT.
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. checked. it is ok.
2. check panel board, clean, & tight all loose parts. clean and tight loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.it is ok. working properly.

CT.
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. checked. it is ok.
2. check panel board, clean, & tight all loose parts. clean and tight loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.it is ok. working properly.

HT.
1. check motor condition ( amp, volt, and connectivity) if the noise coming than inform. checked. it is ok.
2. check panel board, clean, & tight all loose parts. clean and tight loose parts.
3. all parts clean by hand blower.
4. check limit switches and its condition. ensure that all limit switches and wires working properly.it is ok. working properly
Remark
FurnaceOther
StatusCompleted