Maintenance Details
| Date | 02 Jul 2020 |
|---|---|
| Start Time | 16:00:01 |
| End Time | 16:30:01 |
| Nature Of Maintenance | Mechanical |
| Equipment | POLLUTION 2 |
| Type of Maintenance | Scheduled Maintenance |
| Details | POLLUTION ID FANS FOR (Furnace 2) 1. open cover and clean dust.clean dust and start. 2. check the balancing of impeller and vibration isolation.vibration is ok.when dust stuck on impeller blades. It's creats vibration. 3. check v belts condition and inform if its on critical stage.it is ok. 4. check foundation bolts and nuts of Plummer blocks.tight. 5. greasing the Plummer blocks.greasing is done. 6. check the duct condition and remove dust from the duct. 7. check stack condition and check its temperature. 8. Motor greasing is done. |
| Remark | |
| Furnace | Other |
| Status | Completed |